New Delhi [India], November 27: The National Consumer Disputes Redressal Commission (NCDRC) has directed Hero Realty Pvt. Ltd. to pay delay compensation at 10.40% per annum simple interest to eligible homebuyers of its Hero Homes project in Sector 88, Mohali. The Commission has also ruled that Preferential Location Charges (PLC) for the North Green Area shall not be payable in four of the connected appeals.
The decision was delivered on November 18, 2026, in Hero Realty Pvt. Ltd. v. Pallavi Tyagi & Anr. (First Appeal No. 25 of 2026), Ashok Kumar Chawla & Anr. v. Hero Homes & Ors. (First Appeal No. 77 of 2026), and 20 connected appeals. The homebuyers were represented before the Commission by their counsel, Sudhir Kathpalia, Advocate.
A two-member Bench comprising Dr. Inder Jit Singh, Presiding Member, and Mr. Shashi Nandkeolyar, Member, considered appeals filed by the builder as well as homebuyers against a common order of the Punjab State Consumer Disputes Redressal Commission dated October 14, 2025. The NCDRC partly allowed the appeals and modified certain directions issued by the State Commission.
Compensation Fixed at 10.40% Per Annum
An important issue before the Commission was the rate of compensation payable for the delay in handing over possession.
The NCDRC observed that it generally awards compensation at 6% per annum where the buyer’s agreement does not provide for a specific rate or provides only a nominal rate. However, it also clarified that a higher rate may be justified where the parties have agreed to it.
In the present matters, communications issued by Hero Realty to certain allottees offered or acknowledged delay compensation at 10.40% per annum simple interest. The Commission also took note of instances in which the builder had paid compensation at that rate.
Considering these communications and the builder’s own commitment, the Commission held that compensation should be calculated at 10.40% per annum simple interest instead of the 9% awarded by the State Commission.
Period and Calculation of Delay Compensation
The Commission identified June 30, 2022, as the extended completion date under RERA and September 4, 2023, as the date of issuance of the Occupation Certificate.
Accordingly, delay compensation is payable for the period beginning June 30, 2022, and continuing until September 4, 2023. Where the offer of possession was made after the issuance of the Occupation Certificate, compensation is payable up to the date of the offer of possession.
The compensation is to be calculated on the amounts paid towards the sale consideration. For amounts paid after June 30, 2022, the applicable compensation will run from the respective dates of payment.
The Commission also directed that amounts already paid by the builder towards delay compensation be adjusted against the amount payable under its order. The calculation is subject to the GST and tax exclusions specified in the judgment.
PLC for North Green Area Disallowed in Four Appeals
The Commission separately considered the issue of Preferential Location Charges collected in connection with the North Green Area.
In First Appeal Nos. 77, 78, 92 and 93 of 2026, the NCDRC directed that PLC relating to the North Green Area shall not be payable.
The issue arose from the homebuyers’ objections to the levy of these charges in relation to the green area, which was subsequently developed or altered for recreational or play-area purposes.
The direction applies specifically to the four appeals identified by the Commission.
State Commission’s Compensation and Litigation Costs Modified
The NCDRC also modified the State Commission’s directions concerning compensation and litigation costs.
The Commission replaced the State Commission’s award of Rs. 35,000 as compensation with litigation costs of Rs. 10,000 per case.
The modification forms part of the changes made to the common order while deciding the connected appeals filed by the builder and the homebuyers.
Builder’s Appeals and Overall Outcome
The ruling also addresses the relevance of written communications issued by developers when determining the compensation payable for delayed possession.
For homebuyers, the decision highlights the importance of retaining allotment documents, buyer agreements, payment records and written communications from developers concerning possession timelines and delay compensation.
The directions in the judgment are applicable to the parties and appeals decided by the Commission, subject to the terms of the order.